Choose the permit route from the actual building, legal use and proposed scope. DOB distinguishes Permit Wizard uses from other commercial projects submitted through Citizen Access; digital plan review uses ProjectDox. A filed application, an issued building permit, a completed inspection and an approved occupancy are different milestones.
DC DOB application preparation; project-specific permit determinations remain with DOB
Select the application path
DOB’s permitting page is the starting source, not a guarantee that every project in a category follows one simple process. Its published routing identifies the following uses. Confirm the current instructions and scope with the design team before submitting.
| Project / permit situation | Published application route | Preparation question |
|---|---|---|
| One- and two-family residential projects, including the listed trade/solar/demolition/raze permits | Permit Wizard | Does the proposed use remain within this category, and is the scope correctly described? |
| Commercial trade work with no building permit required; or work where the building permit has already been obtained | Permit Wizard for the listed circumstances | What building permit or other approval is already in place? |
| Other commercial projects | Citizen Access Portal | Are commercial drawings, zoning/use information and related reviews complete? |
| Plans needing review | ProjectDox digital plan review | Has the application been properly initiated and the complete coordinated plan set supplied? |
Sources: DC Department of Buildings: Permitting in the District of Columbia.
Prepare a coordinated submission
- Identify address and square/suffix/lot; describe current and proposed use and legal unit count.
- Prepare a written scope matching the drawings and budget. Identify structural, mechanical, electrical, plumbing, fire/life-safety and site work.
- Use the appropriate DOB checklists and qualified professionals for the required signed/sealed documents and technical reports.
- Identify linked reviews: historic, zoning relief if needed, public space, utilities, environmental/site work and other scope-specific requirements.
- Track every comment, response, revised sheet and approval. Make the issued plan set available to the contractor.
Do not recycle a neighboring project’s permit list as proof that yours is complete. Different use, lot conditions, scope and work history can change requirements. A contractor price that excludes approval/design work needs corresponding owner budget and schedule lines.
Build a dependency schedule instead of a promised duration
| Milestone | Depends on | Evidence of completion |
|---|---|---|
| Application ready | Defined scope, coordinated plans and required supporting material | Submission checklist and dated application record |
| Issued approval | Applicable reviews and resolved comments | Issued permit / approved documents |
| Work and inspection holds | Approved scope, contractor/trade readiness and inspections | Inspection reports and corrections resolved |
| Closeout / intended occupancy | Required final inspections and occupancy/use conditions | Relevant final records and occupancy authorization where required |
No universal DC permit timeline is asserted here. Record planned dates, dependencies and an allowance for comment/revision cycles. Financing maturity and interest reserve must reflect more than the contractor’s physical work duration.
Historic review is an additional question
For historic property, preservation clearance can affect a building permit involving exterior appearance. HPO clearance of the permit application is the preservation approval; it is not a separate preservation permit. Some matters are handled by staff and others require board review. Do not order irreversible exterior components before the applicable design is established.
Sources: DC Office of Planning: Building permits for historic property.
Changed scope needs a documented decision
A revised layout, changed structural work, service upgrade or proposed additional unit may invalidate assumptions in the original submission and budget. Ask the design team and DOB which revision or additional approval is needed. A change order signed with the contractor does not establish agency approval. Keep work consistent with issued documents and preserve revision records for inspections and lender review.
Connect permits, draws and occupancy
Lender draw inspection and government construction inspection serve different purposes; one does not automatically substitute for the other. Coordinate the actual documents the lender requires with the project inspection schedule. Confirm separately whether the intended use needs a new or changed Certificate of Occupancy.
Sources: DC Department of Buildings: Certificate of Occupancy and zoning questions.
Continue with DC occupancy and use evidence, the draw liquidity planner and the before-purchase diligence workbook. Do not submit an inquiry or a permit merely to test the workflow.
Your evidence worksheet
Record what you found and what remains open. Nothing is submitted or saved automatically. Download a local copy to keep your work before leaving this page. A selected status is your note, not an agency approval.
Sources & update notes
Source review dated October 24, 2026. Access notes distinguish readable guidance from portal entry points. Our calculations are hypothetical analysis, not agency findings or lender offers.
- Permitting in the District of ColumbiaDC Department of Buildings · Guidance reviewed 2026-10-24
- Building permits for historic propertyDC Office of Planning · Guidance reviewed 2026-10-24
- Certificate of Occupancy and zoning questionsDC Department of Buildings · Guidance reviewed 2026-10-24
October 24, 2026: Rewritten with a specific decision framework, primary sources and worked analysis.
Report a correction or changed source. A source-check date does not represent independent professional sign-off.