Authorize a change only after its scope, price, schedule and approval consequences are understood. Keep original budget, approved commitments, pending changes and forecast-to-complete visible as separate amounts.
Washington, DC investor planning. Agency requirements are distinct from our analytical methods; no property-specific approval, market quote or professional sign-off is represented.
Work through this decision
- Describe the condition with photos and drawing references.
- Obtain an itemized proposal including time effects and any permit revision.
- Approve through the contract authority, then update cost, cash and schedule forecasts.
Evidence to collect
| Evidence | How to use it |
|---|---|
| Change register | record request, approval status and funding source. |
| Schedule effect | identify affected critical-path work. |
| Revised documents | match approved construction to the change. |
The mistake to catch before committing
A hypothetical $8,000 change plus one month of $4,000 interest and $1,500 carry costs $13,500 before other effects. Do not approve on the construction amount alone or deduct contingency twice.
Decide whether the proposal is a change, correction or allowance reconciliation
Compare the proposal with the signed scope, approved drawing revision and contract exclusions. New owner scope, concealed conditions, a substituted product and correction of nonconforming work have different contractual implications. Do not accept the label “change order” as proof that the owner owes the amount. Resolve responsibility through the actual agreement and project team.
| Register field | Why it matters |
|---|---|
| Cause and scope baseline | Shows what changed and avoids paying twice for original scope |
| Design/permit impact | Identifies revised documents and any required agency or special-inspection coordination |
| Price build-up | Separates quantities, labor, materials, credits, tax and markup |
| Time impact | Names the affected dependency, available float and revised completion date |
| Authority and funding | Identifies who may approve and whether owner cash or lender eligibility changes |
DC code and special-inspection requirements remain separate from the owner’s commercial approval of a price. An authorized cost change does not itself approve a revised design.
Sources: DC Department of Buildings: DC construction codes and official amendments; DC Department of Buildings: Special Inspection Policy Manual and forms.
Reconcile approved cost with what is still at risk
Hypothetical example: the original work contract is $150,000, approved changes total $12,000, and $90,000 has been paid. The remaining approved commitment is $72,000. A separate pending $8,000 request is shown as exposure, not quietly included in both the commitment and contingency. If a one-month delay adds $6,100 of financing/carry, the pending decision could add $14,100 to whole-project cost.
Record any deletion credit and whether it actually reduces a signed commitment. Review the revised cash schedule, lender consent and equity buffer before instructing work. Emergency safety measures require the responsible professionals’ direction; document authority and cost promptly through the applicable process rather than using an unsigned spreadsheet as a substitute for the contract.
Connect the scope to DC approvals and closeout
Open the DC agency background for this decision
Use the current DOB permit instructions to identify the application route for the actual work and building use. One- and two-family work and commercial projects do not always follow the same intake route. A contractor estimate is not evidence that required permits, trade reviews or inspections are included. Ask the designer and contractor to identify the approval and inspection dependencies in writing.
DOB warns that its integrated 2017 code books do not show amendments adopted after May 29, 2020; Title 12 DCMR is the official text to confirm. A code modernization announcement does not itself establish which provisions govern your application. Record the governing edition and amendments on the design basis.
| Control point | Record to retain |
|---|---|
| Before work | Issued scope, approved drawings, responsibility for each trade and any conditions |
| Before concealment | Required inspection result, approved revision if conditions differ, and dated photos |
| Before final payment | Final results, unresolved deficiencies, warranties, manuals and turnover records |
Sources: DC Department of Buildings: DC construction codes and official amendments; DC Department of Buildings: Permitting in the District of Columbia; DC Department of Buildings: Construction inspection services.
Your evidence worksheet
Record what you found and what remains open. Nothing is submitted or saved automatically. Download a local copy to keep your work before leaving this page. A selected status is your note, not an agency approval.
Sources & update notes
Source review dated October 24, 2026. Access notes distinguish readable guidance from portal entry points. Our calculations are hypothetical analysis, not agency findings or lender offers.
- Permitting in the District of ColumbiaDC Department of Buildings · Guidance reviewed 2026-10-24
- DC construction codes and official amendmentsDC Department of Buildings · Guidance reviewed 2026-10-24
- Construction inspection servicesDC Department of Buildings · Guidance reviewed 2026-10-24
- Special Inspection Policy Manual and formsDC Department of Buildings · Posted manual reviewed 2026-10-24; interior revision identifies May 15, 2023; confirm current project forms with DOB
October 24, 2026: Deepened with change classification, full cash effects and forecast reconciliation; added specific evidence questions and source applicability notes.