Ground-up financing needs a coordinated land, approval, cost, contractor and exit package. Land value plus a construction estimate is not a complete financeable development plan.
Washington, DC investor planning. Agency requirements are distinct from our analytical methods; no property-specific approval, market quote or professional sign-off is represented.
Work through this decision
- Resolve entitlement and utility dependencies.
- Obtain coordinated bids and a draw/interest cash schedule.
- Review completion guarantees, contingency, retainage and maturity.
Evidence to collect
| Evidence | How to use it |
|---|---|
| Approvals | distinguish application, entitlement and issued permits. |
| Budget | include soft costs, site work, interest and exit. |
| Contractor | verify scope, capability and coverage. |
The mistake to catch before committing
A fully committed construction facility may not fund land carry, cost overruns or pre-draw contractor payments. Keep the borrower's liquidity separate from the stated loan amount.
Match the first advance to a buildable, funded delivery plan
For ground-up work, distinguish land control, approved design/entitlements, building/trade permits, utility readiness, executed construction scope and the ability to fund completion. OCC’s CRE handbook discusses bank acquisition/development/construction risk; it is a due-diligence framework, not a private programme offering. Ask the actual lender which milestones and equity requirements control its advances.
| Funding gate | Evidence |
|---|---|
| Land and approvals | Title/access, survey, current use/envelope analysis and actual issued approvals required by the loan |
| Cost to complete | Coordinated drawings, normalized contracts, allowances, contingency and procurement |
| Delivery | Responsible team, utility/public-space path, inspections and realistic programme |
| Cash and repayment | Dated sources/uses, reserve treatment, borrower support and supported sale/takeout alternative |
Sources: Office of the Comptroller of the Currency: Commercial Real Estate Lending, version 2.0; DC Department of Buildings: DC construction codes and official amendments; DC Department of Buildings: Special Inspection Policy Manual and forms.
The lowest supported loan cap leaves the equity requirement
Hypothetically, 75% of $2 million lender-eligible cost gives a $1.5 million cost cap. An assumed 65% of $2.6 million completed value gives $1.69 million. If both apply, $1.5 million is the lower cap before other restrictions. On $2.2 million total investor cost, the permanent funding gap is $700,000. None of those percentages is an available term or proof that future completed value can fund land closing.
Peak temporary cash can be higher if advances reimburse paid work, reserve cash is restricted or ineligible costs occur early. Reconcile land equity treatment with the lender rather than assuming appreciation is accepted as cash equity. Track special-inspection/professional fees and utility activation through final delivery. Stress cost overrun, completion delay and a weaker exit together; an unconditional commitment to finish can outlast the original cash budget.
Compare financing by cash flow and exit obligations
Open the DC agency background for this decision
There is no universal DC investor loan rate, leverage limit, draw speed or seasoning period. Compare written terms for the actual borrower, collateral, scope and exit. Identify what costs are eligible, the valuation basis, funded balance, holdbacks, points base, interest convention, reserves, maturity, extension and payoff terms.
| Question | Underwriting treatment |
|---|---|
| What is funded when? | Put initial proceeds and later reimbursements on a dated cash schedule |
| What accrues? | Compute interest on the contractually defined balance; identify minimum interest and default charges |
| What cash is restricted? | Separate reserves, borrower equity and available operating cash |
| What repays it? | Deduct selling/refinance costs and apply release or prepayment provisions |
For a commercial refinance, size proceeds under every applicable constraint, including lender-defined DSCR, LTV and debt yield where required. A residential DSCR program may compare qualifying rent with PITIA rather than commercial NOI with annual debt service. Do not mix these definitions. Closing taxes are transaction-specific; a refinance or entity transfer should be reviewed for its own tax treatment.
Sources: DC Law Library: DC Code §42-1103: recordation tax; DC Law Library: DC Code §47-903: transfer tax; DC Office of Tax and Revenue: Recorder of Deeds: tax rates and recording questions.
Your evidence worksheet
Record what you found and what remains open. Nothing is submitted or saved automatically. Download a local copy to keep your work before leaving this page. A selected status is your note, not an agency approval.
Sources & update notes
Source review dated October 24, 2026. Access notes distinguish readable guidance from portal entry points. Our calculations are hypothetical analysis, not agency findings or lender offers.
- Permitting in the District of ColumbiaDC Department of Buildings · Guidance reviewed 2026-10-24
- Construction permits and developer servicesDC Water · Guidance reviewed 2026-10-24
- DC Code §42-1103: recordation taxDC Law Library · Guidance reviewed 2026-10-24
- DC Code §47-903: transfer taxDC Law Library · Guidance reviewed 2026-10-24
- Recorder of Deeds: tax rates and recording questionsDC Office of Tax and Revenue · Guidance reviewed 2026-10-24
- Commercial Real Estate Lending, version 2.0Office of the Comptroller of the Currency · Published 2022-03 · Bank supervisory reference reviewed 2026-10-24, including March 2025 update note; not universal private-lender terms
- DC construction codes and official amendmentsDC Department of Buildings · Guidance reviewed 2026-10-24
- Special Inspection Policy Manual and formsDC Department of Buildings · Posted manual reviewed 2026-10-24; interior revision identifies May 15, 2023; confirm current project forms with DOB
October 24, 2026: Deepened with entitlement-to-funding gates and a cost/value constraint example; added specific evidence questions and source applicability notes.